Hit by ‘worst’ power cuts, Pakistan’s mountain region observes Ramadan in darkness

A woman talks with her relatives at her home in Shimshal village of Hunza valley in northern Pakistan, on May 5, 2018. (AFP/File)
Short Url
Updated 06 May 2021
Follow

Hit by ‘worst’ power cuts, Pakistan’s mountain region observes Ramadan in darkness

  • Daily outages of over 20 hours in some districts of Gilgit-Baltistan have pushed locals to come out in the streets in protest
  • Power officials say there is 360MW shortfall in winter and 132MW in summer as federal government promises new power plants

KHAPLU, GHANCHE: In a mountainous region of northern Pakistan that has a high potential to generate energy from hydropower, daily power cuts of up to 20 hours or more in some districts have pushed locals to come out in the streets in protest and observe the holy fasting month of Ramadan in darkness.
Gilgit-Baltistan, the impoverished, mountainous part of the larger Kashmir region, is the gateway of the China-Pakistan Economic Corridor (CPEC) but its residents have so far reaped few rewards of the $65 billion infrastructure project.
Last month, the region’s chief minister, Khalid Khurshid, ordered the provincial secretary power to ensure there were no power cuts at least during the suhoor and iftar meals in Ramadan. When Gilgit-Baltistan went to local assembly polls in November last year, Prime Minister Imran Khan promised to set up hydroelectric power plants. Last week, he announced a Rs370 billion ($2.4 billion) development package for the region, part of which is intended to address the electricity crisis. In a meeting this week between the finance minister of Pakistan and the chief minister of Gilgit-Baltistan, the federal government promised to “undertake several projects for hydel power generation.”
The construction of “the biggest dam in Pakistan’s history,” the Diamer-Bhasha Dam, was inaugurated by PM Khan in July last year. A number of other hydropower projects are also being built in the area, including the Kohala and Neelum Jhelum projects, with the former still under construction and the latter completed in 2019.
But despite the flurry of activity and promises, for now, local businesses and Ramadan and upcoming Eid Al-Fitr celebrations have been largely upended by power outages.




Residents of Chorbat Valley protest against prolonged power outages in Ghanche district of Gilgit-Baltistan, Pakistan, on May 5, 2021 (Photo Courtesy: Social media)

“There is no electricity in our village,” Ghulam Nabi Sanai from Ghanche district told Arab News on Wednesday. “We registered complaints about the absence of electricity, but no power department officials heard us. That’s why we had to stage a sit-in.”
For the past few days, Sanai said, residents of his hometown had been preparing, and eating, their iftar and suhoor meals in darkness.
Large-scale construction of new power plants — largely coal-fired ones funded by China — has dramatically boosted the country’s energy capacity in the last couple of years. But even as supply surges, electric power is still not reaching up to 50 million people in Pakistan who need it, according to a 2018 World Bank report, though expansion of transmission lines is planned.
Power outages also remain common.
Sher Ali Rana, a tailor in Ghanche, said he normally sewed some 400 outfits for Eid Al-Fitr, the festival to mark the end of Ramadan, when it is a common practice for Muslims to buy new clothes. This year, however, he would hardly be able to make 150 dresses due to electricity shortages.
“Our tailor community has to face power outages every year, but this year we are facing the worst kinds of load shedding ... there is no electricity for 24 hours,” Rana said.




A tailor poses for a photograph during night time at his shop without electricity in Ghanche district of Gilgit-Baltistan, Pakistan on May 4 , 2021. (AN photo: Nisar Ali)

Locals in many other districts, including Skardu and Gilgit, also complain worsening power cuts have paralyzed their daily lives.
Riaz Ai, an executive engineer at Gilgit-Baltistan’s power department, said a major problem of power supply in the region was that its electricity system was not fully connected to the national grid. Low production capacity of existing power stations was another problem, he said. 
Generation capacity in winter was 92 megawatts while the demand was 452MW, Ali said. In summer, generation capacity was 122MW against a demand of 132MW. 
But the engineer said he was hopeful new projects promised under CPEC would solve the region’s power crisis for good.
“If big projects are launched,” he said, “Gilgit Baltistan has the potential to generate more than thousands of megawatts of electricity.”


Two Pakistani men indicted in $10 million Medicare fraud scheme in Chicago

Updated 12 February 2026
Follow

Two Pakistani men indicted in $10 million Medicare fraud scheme in Chicago

  • Prosecutors say defendants billed Medicare and private insurers for nonexistent services
  • Authorities say millions of dollars in proceeds were laundered and transferred to Pakistan

ISLAMABAD: Two Pakistani nationals have been indicted in Chicago for allegedly participating in a $10 million health care fraud scheme that targeted Medicare and private insurers, the US Justice Department said on Thursday.

A federal grand jury charged Burhan Mirza, 31, who resided in Pakistan, and Kashif Iqbal, 48, who lived in Texas, with submitting fraudulent claims for medical services and equipment that were never provided, according to an indictment filed in the US District Court for the Northern District of Illinois.

Medicare is the US federal health insurance program primarily serving Americans aged 65 and older, as well as certain younger people with disabilities.

“Rooting out fraud is a priority for this Justice Department, and these defendants allegedly billed millions of dollars from Medicare and laundered the proceeds to Pakistan,” Deputy Attorney General Todd Blanche said in a statement.

“These alleged criminals stole from a program designed to provide health care benefits to American seniors and the disabled, not line the pockets of foreign fraudsters,” he added. “We will not tolerate these schemes that divert taxpayer dollars to criminals.”

Prosecutors said that in 2023 and 2024, the defendants and their alleged co-conspirators used nominee-owned laboratories and durable medical equipment providers to bill Medicare and private health benefit programs for nonexistent services.

According to the indictment, Mirza obtained identifying information of individuals, providers and insurers without their knowledge and used it to support fraudulent claims submitted on behalf of shell companies. Iqbal was allegedly linked to several durable medical equipment providers that filed false claims and is accused of laundering proceeds and coordinating transfers of funds to Pakistan.

Mirza faces 12 counts of health care fraud and five counts of money laundering. Iqbal is charged with 12 counts of health care fraud, six counts of money laundering and one count of making a false statement to US law enforcement. Arraignments have not yet been scheduled.

Three additional defendants, including an Indian, previously charged in the investigation, have pleaded guilty to federal health care fraud charges and are awaiting sentencing.

An indictment contains allegations, and the defendants are presumed innocent unless proven guilty in court.